Each job has its own estimate. Compare each actual time against the estimate on that same row.
Count the strict comparisons
Put 20, 35, 10, and 40 in B2:B5 and actuals 23, 35, 8, and 42 in C2:C5. Use =SUMPRODUCT(--(C2:C5>B2:B5)). The comparison yields two TRUE values, and the double minus makes them ones.

Illustrated row comparison. Equal actual and estimated times do not count.
Clear one estimate to test the guard
For blanks, use =SUMPRODUCT(--ISNUMBER(B2:B5),--ISNUMBER(C2:C5),--(C2:C5>B2:B5)). Clear B2 in a scratch copy and expect 1. If a source cell contains an error, review it separately. Restore B2 and change the tied actual of 35 to 36 to verify that the strict count increases to 3.

Illustrated numeric-pair guard. Review source errors separately.