Someone needs to review the exhibit labels after drafting finishes. Link the review to the draft’s task ID so a longer draft also moves the review.
Give the draft a stable identifier
```mermaid
gantt
title Exhibit labels
dateFormat YYYY-MM-DD
Draft labels :draft, 2026-12-01, 2d
Review labels :review, after draft, 1d
```In a Markdown preview with Mermaid support, check that the review begins after Draft labels.

Illustrated Gantt dependency. The review refers to the ID, not the display name.
Change 2d to 3d in a scratch copy
Render again. The draft should end one day later and the review should move with it. If the review stays fixed, check for an explicit review date or a mistyped task ID. Add the sentence “Review starts after the draft labels are ready” below the diagram so readers can follow the dependency in plain text.

Illustrated dependency test. Keep a sentence below the diagram for plain-text readers.