Signage can be printed while someone collects the room key. Check-in can open after both jobs finish. A single vertical list can make parallel jobs look sequential, so give them separate paths.
Draw the join before the next task
Put Print signs on the upper branch and Collect room key on the lower branch. Draw both connectors into a small node labeled Both ready. Draw one outgoing arrow to Open check-in desk. Keep the paths short enough that nobody mistakes one line for a dependency between the first two tasks.

Illustrated dependency. The two tasks can overlap, and both are required at the join.
Test the incomplete case
Suppose the signs are ready at 08:45, but the key holder arrives at 08:55. Use the diagram to read back whether the desk can open at 08:45. It stays closed until the key arrives and someone confirms both prerequisites.

Illustrated readiness check. A completed branch alone cannot release the next step.
If you add names or expected completion times, place them beside the task they belong to. Check that these notes cannot be read as extra branches or as permission to skip the join.