Signage can be printed while someone collects the room key. Check-in can open after both jobs finish. A single vertical list can make parallel jobs look sequential, so give them separate paths.

Draw the join before the next task

Put Print signs on the upper branch and Collect room key on the lower branch. Draw both connectors into a small node labeled Both ready. Draw one outgoing arrow to Open check-in desk. Keep the paths short enough that nobody mistakes one line for a dependency between the first two tasks.

Print signs and collect the room key converge at Both ready before the check-in desk opens.

Illustrated dependency. The two tasks can overlap, and both are required at the join.

Test the incomplete case

Suppose the signs are ready at 08:45, but the key holder arrives at 08:55. Use the diagram to read back whether the desk can open at 08:45. It stays closed until the key arrives and someone confirms both prerequisites.

The example shows signs ready but the key pending, leaving the desk closed.

Illustrated readiness check. A completed branch alone cannot release the next step.

If you add names or expected completion times, place them beside the task they belong to. Check that these notes cannot be read as extra branches or as permission to skip the join.