The delivery procedure tells staff to take the west lift. The team has yet to confirm it runs during early unloading. Put that assumption where a reviewer can see what would change if it is wrong.
Record the premise and who can verify it
Use one row for “West lift available from 07:00.” Name the facilities contact as owner. Ask for the lift operating schedule before approval and link the assumption to step 4. Record the fallback, such as the loading ramp, only after checking that it is available and appropriate for the load.

Illustrated register. State what has to be checked and who can check it.
Close the assumption with evidence
Record the check date and result. If the lift opens later, update the affected step and its route diagram before issuing the procedure. If it opens as assumed, retain the confirming source beside the resolved row.

Illustrated consequence. Update the affected step once the evidence arrives.
Read the current draft and check which steps still rely on unresolved assumptions. Put those decisions in front of the reviewer before sign-off.